Yangzijiang Shipbuilding (BS6) · Industrials
Yangzijiang Shipbuilding FY2025 earnings: summary, key numbers & outlook
Results filed 25 Feb 2026 · Quarter ended 31 Dec 2025
Slides (23 pages)Press release ↗Investor relations ↗
Summaries and transcripts are machine-generated and can contain errors.
In brief
Yangzijiang Shipbuilding's order intake recovered in the second half of 2025, leaving a US$22.4 billion orderbook for 245 vessels running to 2030 as it prices remaining 2029 slots and opens 2030.
Yangzijiang Shipbuilding delivered 56 vessels, meeting its target, and won US$2.5 billion of new contracts, about 80% of them in the second half after tariff uncertainty had delayed shipowners' decisions. The product mix shifted toward oil tankers and gas carriers while containerships stayed the largest part of the orderbook. Customers were concentrated in Europe, with Greece, France and Denmark growing as markets.
Management is steering toward filling the remaining 2029 delivery slots and progressively opening 2030, with a US$4.5 billion order-win target for 2026. It is also building Project Hongyuan, a capacity expansion, and an LNG terminal business. The tension is that 2026 deliveries are targeted lower than 2025's, and the group depends on a few large customers and on ordering demand staying firm.
No call transcript for this quarter, so this summary also draws on: Baird Maritime ↗, iMarine News ↗.
Slides & documents
Open the slide deck (PDF, 23 pages) ↗
Showing the first 6 of 23 pages.
Results documents
Key numbers
- Revenue
- RMB28.5 billion
- Net profit attributable to equity holders
- RMB8.6 billion
- Gross profit margin
- 34.2%
- Basic and diluted EPS (RMB cents per share)
- 219.23
- Net cash provided by operating activities (RMB'000)
- 4.5B
up 7.4% from a year ago
up 30.2% from a year ago
up 5.5 ppts from a year ago
up from 167.91 a year ago
down from 12,961,071 a year ago
| Segment or metric | Value | Change |
|---|---|---|
| Shipbuilding revenue | RMB26.8 billion | up 6.4% from a year ago |
| Shipping revenue | RMB1.1 billion | down 8.1% from a year ago |
| Oil tanker construction revenue (RMB'000) | 8.0B | up from 3,003,308 a year ago |
| Outstanding orderbook | US$22.4 billion | |
| Vessels delivered | 56 vessels | |
| Contract wins | US$2.5 billion | about 80% secured in 2H2025 |
Where each number comes from
- Revenue: “Revenue rose 7.4% yoy to RMB28.5 billion in FY2025, primarily driven by progressive construction of vessels secured at higher prices.”
- Net profit attributable to equity holders: “Consequently, profit attributable to equity holders increased by 30.2% yoy to a new high of RMB8.6 billion for FY2025.”
- Gross profit margin: “Gross profit grew by 28.3% yoy to RMB9.8 billion while gross profit margin expanded by 5.5 ppts to 34.2%, mainly supported by stronger newbuild pricing and lower raw material costs.”
- Basic and diluted EPS (RMB cents per share): “Earnings per share attributable to equity holders of the Company (expressed in RMB cents per share) – Basic and diluted 219.23 167.91 113.22 90.50”
- Net cash provided by operating activities (RMB'000): “Net cash provided by operating activities 4,464,550 12,961,071 Cash flows from investing activities Proceeds from sales of property, plant and equipment”
- Shipbuilding revenue: “Shipbuilding revenue closed at RMB26.8 billion, up 6.4% yoy. The increase was mainly driven by steady progress in vessel construction contracted at higher newbuild prices during the reporting period.”
- Shipping revenue: “Revenue from the shipping business declined 8.1% yoy to RMB1.1 billion for FY2025, while gross profit margin narrowed to 28.4% from 43.3% in the preceding year.”
- Oil tanker construction revenue (RMB'000): “Construction of oil tankers 7,997,466 3,003,308 Construction of gas carriers 436,062 - Sales of steel parts 248,436 229,185”
- Outstanding orderbook: “the Group’s total outstanding orderbook stood at US$22.4 billion for 245 vessels, with deliveries spanning from 2026 to 2030.”
- Vessels delivered: “In FY2025, the Group delivered a total of 56 vessels, including 11 vessels delivered by the Group’s joint venture, Yangzi- Mitsui Shipbuilding Co. Ltd (“YAMIC”)”
- Contract wins: “This disciplined approach enabled us to secure US$2.5 billion in contract wins for the year, of which approximately 80% was secured in 2H2025.”
Copied from the press release ↗ and other documents in the company's results page ↗. A figure is published only if its sentence is in those documents.
Outlook
| Metric | Period | Outlook |
|---|---|---|
| Order-win target | FY2026 | US$4.5 billion |
Key takeaways
Order momentum recovered after a tariff-hit first half
Contract wins of US$2.5 billion for 2025 were about 80% secured in 2H2025, after tariff announcements and macro uncertainty delayed shipowners' ordering decisions earlier in the year. Management says the momentum has carried into 2026.
Orderbook now stretches to 2030 delivery slots
The US$22.4 billion orderbook covers 245 vessels with deliveries from 2026 to 2030. Management is prioritising the remaining 2029 slots while progressively opening 2030, which gives long visibility but means pricing for future slots is being set now.
Product mix shifted toward tankers and gas carriers
Oil tanker construction revenue rose to RMB7,997 million from RMB3,003 million, and gas carrier construction began contributing. The company says demand is rotating from large containerships toward mid-sized containerships and oil tankers.
YAMIC repositioning toward gas carriers is paying off
The Yangzi-Mitsui joint venture was repositioned in 2024 toward higher-end gas carriers, which are now about 49% of its orderbook by contract value. Its revenue and net profit both grew in FY2025, and it delivered 11 of the group's 56 vessels.
Capacity expansion and LNG terminal are under construction
Project Hongyuan is due to complete by end-2026, with steel fabrication already begun in 1Q2026, alongside an LNG terminal business (~RMB3.0 billion capex) and LNG storage tank facilities (~RMB2.0 billion capex). The earlier Project Runze expansion was terminated in 2025, which is why the 2026 delivery target is lower.
Questions
What is Yangzijiang Shipbuilding's order target for 2026 and which delivery slots is it selling?
It set a 2026 order-win target of US$4.5 billion, up from US$2.5 billion won in 2025. It is focused on securing the remaining 2029 delivery slots while progressively opening 2030 positions.
What changed in demand for Yangzijiang's vessels during 2025?
Ordering was delayed in 1H2025 by tariff announcements and macro uncertainty, then recovered in 2H2025, when about 80% of the year's contract wins were secured. Management cites fleet replacement needs and a rotation from large containerships toward mid-sized containerships and oil tankers.
What vessel types make up Yangzijiang's orderbook?
Containerships are the largest group with 130 vessels, followed by 49 bulk carriers, 40 oil tankers and 26 LPG, VLAC and VLEC gas carriers. Green vessels account for about 71% of orderbook value.
What expansion projects is Yangzijiang pursuing?
Project Hongyuan, a shipyard capacity expansion, is scheduled for completion by end-2026, and an LNG terminal and LNG storage tank facilities are under construction for completion by end-2026 and 1H2027 respectively. The earlier Project Runze expansion was terminated in 2025.
Why is Yangzijiang's 2026 delivery target lower than 2025's?
The target is 56 vessels, down from 58 previously targeted for 2025. The company attributes the lower target mainly to excluding the capacity expansion once planned under Project Runze, and says 2026 deliveries mainly come from orders placed in 2023 and 2024.