Venture Global (VG) · Energy

Venture Global Q3 2026 earnings: summary, key numbers & outlook

Results filed 10 Nov 2026 · Quarter ended 30 Sep 2026

Press release ↗Investor relations ↗

Summaries and transcripts are machine-generated and can contain errors.

In brief

Venture Global started commercial operations at Plaquemines Phase 1 and unveiled a plan to add an off-grid AI utility for data centers, backed by frame agreements for up to 16 power islands.

Venture Global reached commercial operations at Plaquemines Phase 1 on October 31, about 53 months after its final investment decision, and has loaded six cargos for long-term customers. It exported 124 cargos in the quarter. It also signed 2.0 MTPA of new or increased 20-year offtake agreements, including ConocoPhillips and China Gas, and says 99% of 2026 cargos are now contracted.

Management is steering toward a second line of business, an off-grid AI utility that sells island-mode power, land, water and gas supply to data centers. It targets first compute capacity in late 2028 and about 5 GW by the end of 2031. The main tension is that this is a new, fast-moving market, and it comes while the company is still building CP2 and the Plaquemines and CP2 expansions.

No call transcript for this quarter, so this summary also draws on: Oil & Gas 360 ↗, 24/7 Wall St. ↗.

Key numbers

Income from operations (Q3) · GAAP
$2.3B

up 74% from Q3 2025

Net income attributable to common stockholders (Q3) · GAAP
$2.5B

up 493% from Q3 2025

Diluted EPS (Q3) · GAAP
$0.96

vs. $0.16 a year ago

Consolidated Adjusted EBITDA (Q3) · non-GAAP
$2.6B

up 69% from Q3 2025

Segment or metricValueChange
LNG cargos exported124up 24% from 100 a year ago
LNG volumes sold (TBtu)465.8up 25% from 373.0 a year ago
Calcasieu cargos produced37
Where each number comes from
  • Income from operations (Q3): “Income from operations | $2,295 | $1,320 | 74% | $5,634 | $3,438 | 64% Net income1 | $2,546 | $429 | 493%”
  • Net income attributable to common stockholders (Q3): “Net income1 | $2,546 | $429 | 493% | $4,381 | $1,193 | 267% Consolidated Adjusted EBITDA2 | $2,583 | $1,525 | 69%”
  • Diluted EPS (Q3): “Net income attributable to common stockholders per share—diluted | $0.96 | $0.16 | $1.66 | $0.45”
  • Consolidated Adjusted EBITDA (Q3): “Consolidated Adjusted EBITDA2 | $2,583 | $1,525 | 69% | $6,446 | $4,264 | 51% LNG volumes exported: Cargos | 124 | 100 | 24%”
  • LNG cargos exported: “LNG volumes exported: Cargos | 124 | 100 | 24% | 381 | 252 | 51% TBtu | 467.1 | 371.8 | 26%”
  • LNG volumes sold (TBtu): “LNG volumes sold (TBtu) | 465.8 | 373.0 | 25% | 1,413.0 | 930.5 | 52%”
  • Calcasieu cargos produced: “In the third quarter, the Calcasieu facility produced 37 cargos in line with prior expectations and surpassing our SPA obligations.”

Copied from the press release ↗ and other documents in the SEC filing ↗. A figure is published only if its sentence is in those documents.

From the filingQ3 2026vs year agovs last quarter
Revenue$4.8B+42.9%+3.9%
Operating income$2.3B+73.9%+4.9%
Net income$2.6B+377.8%+85.5%
Diluted EPS$0.96+500.0%+88.2%
Free cash flow-$1.9B−37.1%−17.4%
Operating margin48.3%+8.6 pts+0.5 pts

Calculated by code from XBRL, not by the model.

Outlook

MetricPeriodOutlook
Consolidated Adjusted EBITDAfull year 2026$10.0 billion - $10.3 billion
Calcasieu cargo exports2026152 - 154 cargos
Plaquemines cargo exports2026357 - 364 cargos
Assumed liquefaction fee for unsold cargos2026$21.00/MMBtu - $22.00/MMBtu

Key takeaways

  1. Plaquemines Phase 1 reached commercial operations in record time

    Commercial operations began October 31, just over 53 months after the final investment decision, and six cargos have been loaded for long-term customers. Phase 2 remains on target for mid-2027.

  2. CP2 first LNG pulled forward to mid-year 2027

    With 24 of 36 liquefaction modules on site, management tightened the start of production to roughly two years after Phase 1 FID. The 10 mtpa CP2 expansion is targeting FID in early 2027 and first production in late 2028.

  3. Venture Global proposes an off-grid AI utility for data centers

    The company would offer island-mode power, land, closed-loop water, American natural gas and in-house EPC as a turnkey package. It frames this as an extension of its LNG capabilities that could deliver power ahead of grid-connected timelines.

  4. Frame agreements secure scarce power equipment

    Agreements with GE Vernova and Baker Hughes Energy Services cover up to 16 new 720 MW power islands plus transformer and grid equipment. They give a flexible, staged route to some of the scarcest resources in the market.

  5. New 20-year contracts add 2.0 MTPA of offtake

    ConocoPhillips will buy 1.0 mtpa starting in 2030 and China Gas 0.5 mtpa starting at CP2 Expansion COD. An existing high credit quality customer increased its 20-year SPA by 0.5 mtpa.

Charts

Revenue$4.8B+42.9% y/yQ3 2026
Q4 2024: $1.5B (worked out from the annual figure)Q4 ’24$1.5BQ1 2025: $2.9BQ1 ’25$2.9BQ2 2025: $3.1BQ2 ’25$3.1BQ3 2025: $3.3BQ3 ’25$3.3BQ4 2025: $4.4B (worked out from the annual figure)Q4 ’25$4.4BQ1 2026: $4.6BQ1 ’26$4.6BQ2 2026: $4.6BQ2 ’26$4.6BQ3 2026: $4.8BQ3 ’26$4.8B

Fourth quarter worked out from the annual figure.

Data
Q4 2024$1.5B *
Q1 2025$2.9B
Q2 2025$3.1B
Q3 2025$3.3B
Q4 2025$4.4B *
Q1 2026$4.6B
Q2 2026$4.6B
Q3 2026$4.8B
Diluted EPS (GAAP)$0.96+500.0% y/yQ3 2026
Q1 2025: $0.15Q1 ’25$0.15Q2 2025: $0.14Q2 ’25$0.14Q3 2025: $0.16Q3 ’25$0.16Q1 2026: $0.19Q1 ’26$0.19Q2 2026: $0.51Q2 ’26$0.51Q3 2026: $0.96Q3 ’26$0.96
Data
Q1 2025$0.15
Q2 2025$0.14
Q3 2025$0.16
Q1 2026$0.19
Q2 2026$0.51
Q3 2026$0.96

Fourth-quarter EPS appears once the press release is read; filings report it only for the full year.

Operating margin48.3%+8.6 pts y/yQ3 2026
Q4 2024: 39.0%Q4 ’2439.0%Q1 2025: 37.3%Q1 ’2537.3%Q2 2025: 33.5%Q2 ’2533.5%Q3 2025: 39.7%Q3 ’2539.7%Q4 2025: 38.7%Q4 ’2538.7%Q1 2026: 25.0%Q1 ’2625.0%Q2 2026: 47.8%Q2 ’2647.8%Q3 2026: 48.3%Q3 ’2648.3%
Data
Q4 202439.0%
Q1 202537.3%
Q2 202533.5%
Q3 202539.7%
Q4 202538.7%
Q1 202625.0%
Q2 202647.8%
Q3 202648.3%
Free cash flow-$1.9B−37.1% y/yQ3 2026
Q4 2024: -$3.0BQ4 ’24-$3.0BQ1 2025: -$2.4BQ1 ’25-$2.4BQ2 2025: -$1.5BQ2 ’25-$1.5BQ3 2025: -$1.4BQ3 ’25-$1.4BQ4 2025: -$1.5BQ4 ’25-$1.5BQ1 2026: -$2.4BQ1 ’26-$2.4BQ2 2026: -$1.6BQ2 ’26-$1.6BQ3 2026: -$1.9BQ3 ’26-$1.9B
Data
Q4 2024-$3.0B
Q1 2025-$2.4B
Q2 2025-$1.5B
Q3 2025-$1.4B
Q4 2025-$1.5B
Q1 2026-$2.4B
Q2 2026-$1.6B
Q3 2026-$1.9B

Operating cash flow minus capital expenditure, from cash flow statements.

Questions

What did Venture Global launch or complete this quarter?

Plaquemines Phase 1 reached commercial operations on October 31, 2026, and the company has since loaded six cargos for its SPA customers. It also announced frame agreements to support a potential AI utility business.

What is Venture Global's AI utility plan?

It would offer data centers off-grid island-mode power, land, closed-loop water, American natural gas supply and in-house EPC as one package. Management believes it can begin delivering compute capacity in late 2028 and scale to approximately 5 GW by the end of 2031.

When do CP2 and the expansion projects come online?

CP2 first LNG is now targeted for mid-year 2027. The 10 mtpa CP2 expansion is targeting FID in early 2027 and first production in late 2028, and the Plaquemines expansion is targeting FID in mid 2027 and first LNG in 2029, subject to regulatory approvals.

Who signed new long-term LNG contracts?

ConocoPhillips signed a 20-year SPA for 1.0 mtpa starting in 2030, and China Gas signed one for 0.5 mtpa starting at COD of the CP2 Expansion Project. An existing customer also raised its 20-year SPA by 0.5 mtpa.

What are the main risks to the strategy?

The company cites its need for significant additional capital, regulatory approvals for expansions, and its ability to compete in the rapidly evolving data center infrastructure industry. Pending arbitrations and legal proceedings are also listed as risks.