# Venture Global (VG) Q3 2026 earnings

Results filed 2026-11-10 for the quarter ended 2026-09-30. Source page: https://earnings.opennash.com/companies/vg/2026-q3/
Press release and documents: https://www.sec.gov/Archives/edgar/data/2007855/000200785526000091/0002007855-26-000091-index.htm
> Summaries and transcripts are machine-generated and can contain errors.

## In brief

Venture Global started commercial operations at Plaquemines Phase 1 and unveiled a plan to add an off-grid AI utility for data centers, backed by frame agreements for up to 16 power islands.

Venture Global reached commercial operations at Plaquemines Phase 1 on October 31, about 53 months after its final investment decision, and has loaded six cargos for long-term customers. It exported 124 cargos in the quarter. It also signed 2.0 MTPA of new or increased 20-year offtake agreements, including ConocoPhillips and China Gas, and says 99% of 2026 cargos are now contracted.
Management is steering toward a second line of business, an off-grid AI utility that sells island-mode power, land, water and gas supply to data centers. It targets first compute capacity in late 2028 and about 5 GW by the end of 2031. The main tension is that this is a new, fast-moving market, and it comes while the company is still building CP2 and the Plaquemines and CP2 expansions.

## Key numbers

| Metric | Value | Change | Basis |
| --- | --- | --- | --- |
| Income from operations (Q3) | $2.3B | up 74% from Q3 2025 | GAAP |
| Net income attributable to common stockholders (Q3) | $2.5B | up 493% from Q3 2025 | GAAP |
| Diluted EPS (Q3) | $0.96 | vs. $0.16 a year ago | GAAP |
| Consolidated Adjusted EBITDA (Q3) | $2.6B | up 69% from Q3 2025 | non-GAAP |

## Segments and operating metrics

| Name | Value | Change |
| --- | --- | --- |
| LNG cargos exported | 124 | up 24% from 100 a year ago |
| LNG volumes sold (TBtu) | 465.8 | up 25% from 373.0 a year ago |
| Calcasieu cargos produced | 37 |  |

## Outlook

| Metric | Period | Outlook |
| --- | --- | --- |
| Consolidated Adjusted EBITDA | full year 2026 | $10.0 billion - $10.3 billion |
| Calcasieu cargo exports | 2026 | 152 - 154 cargos |
| Plaquemines cargo exports | 2026 | 357 - 364 cargos |
| Assumed liquefaction fee for unsold cargos | 2026 | $21.00/MMBtu - $22.00/MMBtu |

## Key takeaways

1. **Plaquemines Phase 1 reached commercial operations in record time** Commercial operations began October 31, just over 53 months after the final investment decision, and six cargos have been loaded for long-term customers. Phase 2 remains on target for mid-2027.
2. **CP2 first LNG pulled forward to mid-year 2027** With 24 of 36 liquefaction modules on site, management tightened the start of production to roughly two years after Phase 1 FID. The 10 mtpa CP2 expansion is targeting FID in early 2027 and first production in late 2028.
3. **Venture Global proposes an off-grid AI utility for data centers** The company would offer island-mode power, land, closed-loop water, American natural gas and in-house EPC as a turnkey package. It frames this as an extension of its LNG capabilities that could deliver power ahead of grid-connected timelines.
4. **Frame agreements secure scarce power equipment** Agreements with GE Vernova and Baker Hughes Energy Services cover up to 16 new 720 MW power islands plus transformer and grid equipment. They give a flexible, staged route to some of the scarcest resources in the market.
5. **New 20-year contracts add 2.0 MTPA of offtake** ConocoPhillips will buy 1.0 mtpa starting in 2030 and China Gas 0.5 mtpa starting at CP2 Expansion COD. An existing high credit quality customer increased its 20-year SPA by 0.5 mtpa.

## Questions

**What did Venture Global launch or complete this quarter?** Plaquemines Phase 1 reached commercial operations on October 31, 2026, and the company has since loaded six cargos for its SPA customers. It also announced frame agreements to support a potential AI utility business.
**What is Venture Global's AI utility plan?** It would offer data centers off-grid island-mode power, land, closed-loop water, American natural gas supply and in-house EPC as one package. Management believes it can begin delivering compute capacity in late 2028 and scale to approximately 5 GW by the end of 2031.
**When do CP2 and the expansion projects come online?** CP2 first LNG is now targeted for mid-year 2027. The 10 mtpa CP2 expansion is targeting FID in early 2027 and first production in late 2028, and the Plaquemines expansion is targeting FID in mid 2027 and first LNG in 2029, subject to regulatory approvals.
**Who signed new long-term LNG contracts?** ConocoPhillips signed a 20-year SPA for 1.0 mtpa starting in 2030, and China Gas signed one for 0.5 mtpa starting at COD of the CP2 Expansion Project. An existing customer also raised its 20-year SPA by 0.5 mtpa.
**What are the main risks to the strategy?** The company cites its need for significant additional capital, regulatory approvals for expansions, and its ability to compete in the rapidly evolving data center infrastructure industry. Pending arbitrations and legal proceedings are also listed as risks.