BHP (BHP) · Mining
BHP Q4 FY2026 earnings: summary, key numbers & outlook
Results filed 19 Aug 2026 · Quarter ended 30 Jun 2026
Press release ↗Investor relations ↗
Summaries and transcripts are machine-generated and can contain errors.
In brief
Copper contributed more than half of BHP's earnings for the first time, as Jansen potash nears first production in mid-CY2027 and a new CEO takes over.
BHP produced around 2 Mt of copper for the second year running and remained the world's largest copper producer, with copper contributing more than half of Underlying EBITDA for the first time. WAIO set a record for iron ore production and kept its position as the lowest-cost major producer. BMA lifted steelmaking coal output. Jansen Stage 1 is 84 per cent complete, and Spence sanctioned two sustaining growth projects.
Brandon Craig became CEO on 1 July 2026 and set three pillars: faster performance, disciplined programmatic growth, and stronger foundations with governments and communities. BHP aims for copper-equivalent growth of around 3–4 per cent a year from FY2027 to FY2035. The tension is execution: Jansen's cost and schedule were reset, Escondida's ore grade is declining, copper output fell 3% year on year, and a contractor fatality at Peak Downs in July 2026 sharpens the safety focus.
No call transcript for this quarter, so this summary also draws on: Hargreaves Lansdown ↗, SMM (Shanghai Metals Market) ↗, The Rio Times ↗.
Key numbers
- Attributable profit
- US$9.8bn
- Underlying earnings per share · non-GAAP
- 260.0USc
FY2025: US$9.0 bn
FY2025: 200.2 USc
| Segment or metric | Value | Change |
|---|---|---|
| Copper production | around 2 million tonnes (Mt) | for the second year running |
| Dividend per share | 172 US cents | up 62 US cents on FY2025 |
| Net debt | US$8.7 billion |
Where each number comes from
- Attributable profit: “US$9.8bn 260.0USc 172USc 33% FY2025: US$9.0 bn FY2025: 200.2 USc FY2025: 110 USc on FY2020 baseline”
- Underlying earnings per share: “US$9.8bn 260.0USc 172USc 33% FY2025: US$9.0 bn FY2025: 200.2 USc FY2025: 110 USc on FY2020 baseline”
- Copper production: “We produced around 2 million tonnes (Mt) of copper in FY2026 for the second year running as global copper prices hit record levels and supply remained constrained.”
- Dividend per share: “Your Board determined dividends totalling 172 US cents a share for FY2026, an increase of 62 US cents on FY2025.”
- Net debt: “we have maintained a strong balance sheet with net debt decreasing to US$8.7 billion at 30 June 2026”
Copied from the press release ↗ and other documents in the SEC filing ↗. A figure is published only if its sentence is in those documents.
Outlook
| Metric | Period | Outlook |
|---|---|---|
| Group copper production | FY2027 group copper production | 1.65–1.8 million mt |
| Escondida copper production | FY2027 Escondida copper production | 1–1.1 million mt |
| WAIO production (100 per cent basis) | Q4 FY2028 | >305 Mtpa |
| Copper-equivalent production growth, compound annual | FY2027 to FY2035 | around 3–4 per cent a year |
Key takeaways
Copper now drives most of BHP's earnings
Copper contributed more than half of Underlying EBITDA for the first time, at a 70 per cent EBITDA margin. BHP produced around 2 Mt for the second year running and stays the world's largest copper producer.
Jansen potash is 84% built, first output mid-2027
Jansen Stage 1 is 84 per cent complete after an update on cost and schedule earlier in the year. BHP believes it can eventually supply around 10 per cent of global potash at an earnings margin greater than 60 per cent.
Copper pipeline targets about 5% annual growth
Escondida's new concentrator plans are with Chilean environmental authorities, and Copper South Australia's expansion is in detailed engineering ahead of a final investment decision. Two Spence projects were sanctioned in June, with first production expected from FY2028.
Iron ore expands while holding cost lead
WAIO set a record for annual iron ore production and kept its lowest-cost status for a seventh year, with a cost advantage of more than US$10 per tonne over its nearest Pilbara competitor. BHP plans >305 Mtpa (100 per cent basis) by Q4 FY2028.
New CEO Brandon Craig sets three strategic pillars
Craig, who started 1 July 2026, wants to accelerate performance with technology, deliver sequenced growth including bolt-on acquisitions and partnerships, and strengthen relationships with governments and communities. Exploration spending is set to increase.
Questions
What is the status of BHP's Jansen potash project?
Jansen Stage 1 is 84 per cent complete, with first potash projected in mid-CY2027. BHP's immediate priority is disciplined execution with tighter controls and safe delivery of first production.
How is BHP positioning for copper demand growth?
BHP expects copper demand to rise from ~34 Mtpa today to >50 Mtpa by CY2050, including data centre demand that could grow around sixfold to about 3 Mtpa. It targets copper business growth of around 5 per cent a year from FY2027 to FY2035.
What copper production outlook did BHP give for FY2027?
Third-party reporting of the results puts FY2027 group copper guidance at 1.65–1.8 million mt, with Escondida expected at 1–1.1 million mt. Group copper output fell 3% in FY2026, partly on lower Escondida and Spence volumes.
What changes with Brandon Craig as CEO?
Craig succeeded Mike Henry on 1 July 2026 and framed strategy around accelerating performance, programmatic growth and stronger foundations. He plans more exploration, smaller bolt-on acquisitions and partnerships, with safety as his first priority.
How is BHP using technology and decarbonisation in operations?
BHP is trialling battery-electric haul trucks in the Pilbara and has started a battery-electric locomotives trial. It is also rolling out vehicle proximity detection and AI tools such as the 'Ask Safety' GenAI chatbot, and says renewables supplied 80 per cent of electricity at operated assets.
Documents
SEC filing