American Electric Power Q2 2026 earnings: summary, key numbers & outlook

Results filed 30 Jul 2026 · Quarter ended 30 Jun 2026

Press release ↗Investor relations ↗

Summaries and transcripts are machine-generated and can contain errors.

In brief

AEP added 6 GW of signed load agreements, mostly in Texas, lifting contracted growth to 69 GW through 2030 and securing gas turbines to serve it.

AEP signed an incremental 6 GW of load agreements in the quarter, primarily in Texas, from hyperscalers, data centers and industrials, taking contracted load growth through 2030 to 69 GW. It secured 3 more GW of gas-fired turbine capacity, bringing the total to approximately 13 GW. Virginia approved a large load tariff, making five states with approved tariffs and three more pending. AEP Texas secured a DOE loan for up to $3.3 billion.

Management is steering toward serving this demand with new generation and transmission while arguing that large customers lower costs for existing ones. AEP is evaluating up to 10 GW more turbine capacity and sees more than $10 billion of added investment opportunities beyond its $78 billion plan. The tension is affordability: growth must be backed by take-or-pay contracts and regulatory approvals, and costs must stay manageable for residential customers.

No call transcript for this quarter, so this summary also draws on: The Motley Fool ↗.

Key numbers

Second-quarter revenue ($ in millions)
5.4B

up from 5,087 in second-quarter 2025

GAAP earnings · GAAP
$713 million

down from $1,226 million in second-quarter 2025

GAAP earnings per share · GAAP
$1.31

down from $2.29 in second-quarter 2025

Operating earnings per share · non-GAAP
$1.36

down from $1.43 in second-quarter 2025

Operating earnings · non-GAAP
$742 million

down from $766 million in second-quarter 2025

Segment or metricValueChange
Contracted load growth through 203069 gigawatts (GW)up six GW of signed load agreements in the quarter
Secured gas-fired turbine capacityapproximately 13 GWup three GW in the quarter
DOE loans securedapproximately $5 billionincludes new AEP Texas loan of up to $3.3 billion
Vertically Integrated Utilities operating earnings ($ in millions)302.0Mup from 297
Transmission & Distribution Utilities operating earnings ($ in millions)239.0Mup from 224
AEP Transmission Holdco operating earnings ($ in millions)225.0Mup from 224
T&D Utilities commercial energy delivered (million kWh)12,96117.4% higher
Where each number comes from
  • Second-quarter revenue ($ in millions): “Revenue ($ in millions): | 5,087 | 5,445 | 358 | 10,550 | 11,465 | 915 Earnings ($ in millions): GAAP | 1,226 | 713”
  • GAAP earnings: “reported second-quarter 2026 GAAP earnings of $713 million or $1.31 per share, compared with GAAP earnings of $1,226 million or $2.29 per share in second-quarter 2025.”
  • GAAP earnings per share: “reported second-quarter 2026 GAAP earnings of $713 million or $1.31 per share, compared with GAAP earnings of $1,226 million or $2.29 per share in second-quarter 2025.”
  • Operating earnings per share: “Operating earnings for second-quarter 2026 were $742 million or $1.36 per share, compared with operating earnings of $766 million or $1.43 per share in second-quarter 2025.”
  • Operating earnings: “Operating earnings for second-quarter 2026 were $742 million or $1.36 per share, compared with operating earnings of $766 million or $1.43 per share in second-quarter 2025.”
  • Contracted load growth through 2030: “The company added an incremental six GW of signed load agreements during the second quarter, primarily in Texas, bringing total contracted load growth through 2030 to 69 GW.”
  • Secured gas-fired turbine capacity: “AEP secured three additional GW of gas-fired turbine capacity, bringing its total secured capacity to approximately 13 GW for potential deployment through 2031.”
  • DOE loans secured: “With this financing, AEP has now secured approximately $5 billion in DOE loans across its portfolio, supporting nearly $1 billion in projected customer savings through lower interest costs.”
  • Vertically Integrated Utilities operating earnings ($ in millions): “Vertically Integrated Utilities (a) | 297 | 302 | 5 | 647 | 766 | 119 Transmission & Distribution Utilities (b) | 224 | 239 | 15 |”
  • Transmission & Distribution Utilities operating earnings ($ in millions): “Vertically Integrated Utilities (a) | 297 | 302 | 5 | 647 | 766 | 119 Transmission & Distribution Utilities (b) | 224 | 239 | 15 |”
  • AEP Transmission Holdco operating earnings ($ in millions): “AEP Transmission Holdco (c) | 224 | 225 | 1 | 459 | 434 | (25) Generation & Marketing (d) | 92 | 91 | (1) | 168 | 181 | 13”
  • T&D Utilities commercial energy delivered (million kWh): “Transmission & Distribution Utilities Retail: Residential | 6,299 | 6,119 | (2.9)% Commercial | 11,042 | 12,961 | 17.4% Industrial | 7,048 | 8,104 | 15.0%”

Copied from the press release ↗ and other documents in the SEC filing ↗. A figure is published only if its sentence is in those documents.

XBRL figures for this quarter arrive with the 10-Q or 10-K; the numbers above are from the press release.

Outlook

MetricPeriodOutlook
Operating earnings per share guidance (raised from $6.15 to $6.45)full-year 2026$6.25 to $6.55 per share
GAAP EPS guidance equivalentfull-year 2026$6.16 to $6.46 per share
Five-year capital plan2026 through 2030$78 billion
Annual operating earnings growth ratethrough 20307% to 9%

Key takeaways

  1. Contracted load growth reaches 69 GW through 2030

    AEP added an incremental six GW of signed agreements in the quarter, primarily in Texas, from hyperscalers, data centers and industrials. This shows demand is converting into signed commitments rather than inquiries.

  2. Gas turbine reservations expand to about 13 GW

    AEP secured three additional GW of gas-fired turbine capacity for potential deployment through 2031 and is evaluating up to 10 GW more through 2035. Securing equipment early gives it flexibility to serve load growth reliably.

  3. Large load tariffs now approved in five states

    Virginia approved a large load tariff this quarter, with three additional state filings pending approval. These tariffs are central to AEP's pitch that growth should help pay for growth.

  4. Affordability case rests on cost offsets and DOE funding

    AEP identified up to $16 billion in expected cost offsets for residential customers, backed by executed take-or-pay agreements. DOE loans and grants are expected to deliver nearly $1.4 billion in customer benefits, including a loan of up to $3.3 billion for AEP Texas.

  5. Regulatory approvals advanced generation and rate relief

    Oklahoma approved adding 1.3 GW of generation, Ohio approved a distribution base rate decrease, and a $1.4 billion securitization let Appalachian Power file its lowest Virginia base rate increase in nearly 30 years. These outcomes support both buildout and affordability.

Charts

Revenue$6.0B+10.2% y/yQ1 2026
Q2 2024: $4.6BQ2 ’24$4.6BQ3 2024: $5.4BQ3 ’24$5.4BQ4 2024: $4.7B (worked out from the annual figure)Q4 ’24$4.7BQ1 2025: $5.5BQ1 ’25$5.5BQ2 2025: $5.1BQ2 ’25$5.1BQ3 2025: $6.0BQ3 ’25$6.0BQ4 2025: $5.3B (worked out from the annual figure)Q4 ’25$5.3BQ1 2026: $6.0BQ1 ’26$6.0B

Fourth quarter worked out from the annual figure.

Data
Q2 2024$4.6B
Q3 2024$5.4B
Q4 2024$4.7B *
Q1 2025$5.5B
Q2 2025$5.1B
Q3 2025$6.0B
Q4 2025$5.3B *
Q1 2026$6.0B
Diluted EPS (GAAP)$1.60+6.7% y/yQ1 2026
Q2 2024: $0.64Q2 ’24$0.64Q3 2024: $1.80Q3 ’24$1.80Q1 2025: $1.50Q1 ’25$1.50Q2 2025: $2.29Q2 ’25$2.29Q3 2025: $1.81Q3 ’25$1.81Q1 2026: $1.60Q1 ’26$1.60
Data
Q2 2024$0.64
Q3 2024$1.80
Q1 2025$1.50
Q2 2025$2.29
Q3 2025$1.81
Q1 2026$1.60

Fourth-quarter EPS appears once the press release is read; filings report it only for the full year.

Operating margin22.6%−0.9 pts y/yQ1 2026
Q2 2024: 14.9%Q2 ’2414.9%Q3 2024: 24.9%Q3 ’2424.9%Q4 2024: 23.3%Q4 ’2423.3%Q1 2025: 23.5%Q1 ’2523.5%Q2 2025: 27.5%Q2 ’2527.5%Q3 2025: 25.3%Q3 ’2525.3%Q4 2025: 21.0%Q4 ’2521.0%Q1 2026: 22.6%Q1 ’2622.6%
Data
Q2 202414.9%
Q3 202424.9%
Q4 202423.3%
Q1 202523.5%
Q2 202527.5%
Q3 202525.3%
Q4 202521.0%
Q1 202622.6%
Free cash flow$554.0M−61.8% y/yQ1 2026
Q3 2024: $2.2BQ3 ’24$2.2BQ4 2024: $1.3BQ4 ’24$1.3BQ1 2025: $1.4BQ1 ’25$1.4BQ2 2025: -$138.2MQ2 ’25-$138.2MQ3 2025: $2.2BQ3 ’25$2.2BQ4 2025: $17.5MQ4 ’25$17.5MQ1 2026: $554.0MQ1 ’26$554.0M
Data
Q3 2024$2.2B
Q4 2024$1.3B
Q1 2025$1.4B
Q2 2025-$138.2M
Q3 2025$2.2B
Q4 2025$17.5M
Q1 2026$554.0M

Operating cash flow minus capital expenditure, from cash flow statements.

Questions

How much new customer demand did AEP sign this quarter?

AEP added an incremental six GW of signed load agreements, primarily in Texas, bringing total contracted load growth through 2030 to 69 GW. Customers include hyperscalers, data centers and industrials.

How is AEP securing generation to serve the new load?

It secured three additional GW of gas-fired turbine capacity, for a total of approximately 13 GW for potential deployment through 2031. It is also evaluating up to 10 GW more through 2035.

How is AEP protecting existing customers from the cost of data center growth?

It is using large load tariffs, now approved in five states with three filings pending, and take-or-pay service agreements. It identified up to $16 billion in expected cost offsets for residential customers in its vertically integrated utilities.

What role is the Department of Energy playing in AEP's plans?

AEP Texas secured a DOE loan for up to $3.3 billion for nearly 100 transmission projects, expected to save customers $685 million in interest. AEP now has approximately $5 billion in DOE loans and almost $400 million in grants, for nearly $1.4 billion in estimated customer benefits.

Is AEP planning investment beyond its current capital plan?

Yes. AEP reports line of sight to incremental capital investments of more than $10 billion, including a fuel cell project in Wyoming, the Piketon transmission opportunity in Ohio and incremental generation in its footprint.