# American Electric Power (AEP) Q2 2026 earnings

Results filed 2026-07-30 for the quarter ended 2026-06-30. Source page: https://earnings.opennash.com/companies/aep/2026-q2/
Press release and documents: https://www.sec.gov/Archives/edgar/data/4904/000000490426000055/0000004904-26-000055-index.htm
> Summaries and transcripts are machine-generated and can contain errors.

## In brief

AEP added 6 GW of signed load agreements, mostly in Texas, lifting contracted growth to 69 GW through 2030 and securing gas turbines to serve it.

AEP signed an incremental 6 GW of load agreements in the quarter, primarily in Texas, from hyperscalers, data centers and industrials, taking contracted load growth through 2030 to 69 GW. It secured 3 more GW of gas-fired turbine capacity, bringing the total to approximately 13 GW. Virginia approved a large load tariff, making five states with approved tariffs and three more pending. AEP Texas secured a DOE loan for up to $3.3 billion.
Management is steering toward serving this demand with new generation and transmission while arguing that large customers lower costs for existing ones. AEP is evaluating up to 10 GW more turbine capacity and sees more than $10 billion of added investment opportunities beyond its $78 billion plan. The tension is affordability: growth must be backed by take-or-pay contracts and regulatory approvals, and costs must stay manageable for residential customers.

## Key numbers

| Metric | Value | Change | Basis |
| --- | --- | --- | --- |
| Second-quarter revenue ($ in millions) | 5.4B | up from 5,087 in second-quarter 2025 |  |
| GAAP earnings | $713 million | down from $1,226 million in second-quarter 2025 | GAAP |
| GAAP earnings per share | $1.31 | down from $2.29 in second-quarter 2025 | GAAP |
| Operating earnings per share | $1.36 | down from $1.43 in second-quarter 2025 | non-GAAP |
| Operating earnings | $742 million | down from $766 million in second-quarter 2025 | non-GAAP |

## Segments and operating metrics

| Name | Value | Change |
| --- | --- | --- |
| Contracted load growth through 2030 | 69 gigawatts (GW) | up six GW of signed load agreements in the quarter |
| Secured gas-fired turbine capacity | approximately 13 GW | up three GW in the quarter |
| DOE loans secured | approximately $5 billion | includes new AEP Texas loan of up to $3.3 billion |
| Vertically Integrated Utilities operating earnings ($ in millions) | 302 | up from 297 |
| Transmission & Distribution Utilities operating earnings ($ in millions) | 239 | up from 224 |
| AEP Transmission Holdco operating earnings ($ in millions) | 225 | up from 224 |
| T&D Utilities commercial energy delivered (million kWh) | 12,961 | 17.4% higher |

## Outlook

| Metric | Period | Outlook |
| --- | --- | --- |
| Operating earnings per share guidance (raised from $6.15 to $6.45) | full-year 2026 | $6.25 to $6.55 per share |
| GAAP EPS guidance equivalent | full-year 2026 | $6.16 to $6.46 per share |
| Five-year capital plan | 2026 through 2030 | $78 billion |
| Annual operating earnings growth rate | through 2030 | 7% to 9% |

## Key takeaways

1. **Contracted load growth reaches 69 GW through 2030** AEP added an incremental six GW of signed agreements in the quarter, primarily in Texas, from hyperscalers, data centers and industrials. This shows demand is converting into signed commitments rather than inquiries.
2. **Gas turbine reservations expand to about 13 GW** AEP secured three additional GW of gas-fired turbine capacity for potential deployment through 2031 and is evaluating up to 10 GW more through 2035. Securing equipment early gives it flexibility to serve load growth reliably.
3. **Large load tariffs now approved in five states** Virginia approved a large load tariff this quarter, with three additional state filings pending approval. These tariffs are central to AEP's pitch that growth should help pay for growth.
4. **Affordability case rests on cost offsets and DOE funding** AEP identified up to $16 billion in expected cost offsets for residential customers, backed by executed take-or-pay agreements. DOE loans and grants are expected to deliver nearly $1.4 billion in customer benefits, including a loan of up to $3.3 billion for AEP Texas.
5. **Regulatory approvals advanced generation and rate relief** Oklahoma approved adding 1.3 GW of generation, Ohio approved a distribution base rate decrease, and a $1.4 billion securitization let Appalachian Power file its lowest Virginia base rate increase in nearly 30 years. These outcomes support both buildout and affordability.

## Questions

**How much new customer demand did AEP sign this quarter?** AEP added an incremental six GW of signed load agreements, primarily in Texas, bringing total contracted load growth through 2030 to 69 GW. Customers include hyperscalers, data centers and industrials.
**How is AEP securing generation to serve the new load?** It secured three additional GW of gas-fired turbine capacity, for a total of approximately 13 GW for potential deployment through 2031. It is also evaluating up to 10 GW more through 2035.
**How is AEP protecting existing customers from the cost of data center growth?** It is using large load tariffs, now approved in five states with three filings pending, and take-or-pay service agreements. It identified up to $16 billion in expected cost offsets for residential customers in its vertically integrated utilities.
**What role is the Department of Energy playing in AEP's plans?** AEP Texas secured a DOE loan for up to $3.3 billion for nearly 100 transmission projects, expected to save customers $685 million in interest. AEP now has approximately $5 billion in DOE loans and almost $400 million in grants, for nearly $1.4 billion in estimated customer benefits.
**Is AEP planning investment beyond its current capital plan?** Yes. AEP reports line of sight to incremental capital investments of more than $10 billion, including a fuel cell project in Wyoming, the Piketon transmission opportunity in Ohio and incremental generation in its footprint.