0:12:16 · Analyst, JPMorgan · Power customers
Who are the customers for the one to two expected behind-the-meter power deals, and could they lead to follow-on projects?
Management is advancing deals with additional high-quality hyperscalers, expects a more diverse customer base and much longer contracts, and expects projects that show more clearly how the backlog scales. — Chad Zamarin
0:14:20 · Analyst, JPMorgan · Socrates learnings
What has Williams learned from running Socrates, and how does it think about expanding its solutions?
Socrates is a clean extension of existing capabilities, Plato South has ramped up as expected, and lessons on commissioning and efficiency are being carried into the next projects. — Chad Zamarin, Larry Larson
0:17:15 · Praneeth Satish, Wells Fargo · Election risk
How sensitive is the timing of power projects, especially in Texas, to the elections?
Management does not see the election as a gating item and says it is focused on scoping, designing and optimizing projects in supportive communities. — Chad Zamarin
0:19:13 · Praneeth Satish, Wells Fargo · SESI 2
How large could SESI 2 become, and will its build multiple match SESI 1?
The project has 150 MMcf/d contracted with a utility and could reach about 390 MMcf/d if a second customer firms up, with a build multiple expected in the four to six times range. — Larry Larson
0:20:41 · Spiro Downits, Citi · Growth targets
What would it take to reach the 16% high end of the compensation target, and how will leverage be kept below four times?
Management points to its backlog in pipes and power, possible bolt-ons and partner capital, with a three and a half to four times leverage target and growing internal cash flow after 2027. — Chad Zamarin, John Porter
0:26:04 · Spiro Downits, Citi · Power equipment
What does the roughly $6 billion of long-lead equipment disclosed in the 10-Q mean for the power opportunity?
The $5.9 billion includes commitments with cancellation fees and backstops and is not tightly tied to the 6 gigawatts, and equipment on order supports the backlog with deliveries into the early 2030s. — John Porter, Chad Zamarin
0:29:03 · Elvira Scotto, RBC Capital Markets · Momentum integration
How is the Momentum integration going relative to plan?
Integration is off to a strong start with no surprises, synergies are being captured ahead of the model, and commercial engagement is strong. — Rob Wingo
0:29:36 · Elvira Scotto, RBC Capital Markets · LNG capacity
How does Williams view its 1.5 million ton per annum Woodside Louisiana LNG capacity as demand for US LNG grows?
It values the capacity more highly and plans to term it out for fixed margin, using it to offer producers international pricing paired with gathering services. — Rob Wingo, Chad Zamarin, Larry Larson
0:33:26 · John McKay, Goldman Sachs · Transco expansion
How much expansion capacity remains on Transco, and on what timing?
Management calls the opportunity almost limitless, with more projects expected to commercialize in 2027, ranging from small expansions to larger ones that extend growth beyond 2030. — Larry Larson, Chad Zamarin
0:35:54 · John McKay, Goldman Sachs · NESE permitting
Where does NESE stand and what are the next steps?
The Third Circuit remanded the New Jersey certificate; Williams says nothing in the opinion jeopardizes the project, but next-winter in-service is at risk and it is backing permitting reform. — Lane Wilson, Chad Zamarin
0:38:50 · Julian DeMoulin-Smith, Jefferies · Project scale
Will new power projects be larger, and are gas lateral easements an issue?
Some backlog projects will be larger and phased, and easements have not prevented projects from advancing because sites are chosen where gas supply can be delivered. — Chad Zamarin
0:42:08 · Julian DeMoulin-Smith, Jefferies · Announcement scope
Would future phases be announced together with the initial scope, making announcements larger?
For some projects, yes: management expects to commercialize a larger portion of the backlog with several phases inside a single project. — Chad Zamarin
0:42:51 · Julian DeMoulin-Smith, Jefferies · Project returns
Is Williams confident returns hold on these larger projects?
Yes, it expects the return framework to hold, with larger and more efficient equipment lowering customer cost while preserving returns. — Chad Zamarin
0:43:56 · Robert Cattelier, RBC Capital Markets · Power financing
What is the appetite for using a joint venture structure again for future power projects?
Pricing has moved since the July deal with Blackstone, but a similar structure remains an option alongside running leverage hotter for a short time. — John Porter
0:45:36 · Robert Cattelier, RBC Capital Markets · Momentum upside
Where is the most strategic upside from Momentum?
Most of the inventory behind the system is economic at about $3.75 gas, and the combined footprint opens new dedications, expansions and downstream Transco opportunities such as Delta Access. — Rob Wingo, Larry Larson, Chad Zamarin
0:48:38 · Manav Gupta, UBS · Storage expansion
What is the outlook for Clay Basin and further storage expansions?
Storage has lagged development, contracted rates are rising, and more Gulf-region storage expansions are expected to be announced in coming quarters. — Larry Larson, Chad Zamarin
0:50:31 · Manav Gupta, UBS · Gathering portfolio
How does Williams view its remaining gathering portfolio after the recent divestitures?
The divestitures were small, non-strategic and mostly off-system, and management likes its gathering footprint given expected demand growth. — Chad Zamarin
0:52:16 · Jason Gableman, TD Cowen · Announcement timing
Does one to two projects by year-end mean one is more certain than the other?
Williams announces only once a commercial agreement is signed and the project is permit-ready, and it expects one or two signed by year-end with more in 2027 and beyond. — Chad Zamarin
0:53:57 · Jason Gableman, TD Cowen · Financing disclosure
Will financing for new power projects be announced alongside project sanction?
For large projects Williams will try to give color on how the project scales and how it plans to finance it, though how specific that is will vary. — John Porter
0:55:03 · Craig Shear, TUI Brothers · Project economics
Do longer tenors on new projects de-risk them while limiting upside beyond the five-times economics?
Williams targets maintaining economics through efficiency, built on fee-based take-or-pay cash flows, and does not embed speculative upside in base economics. — Chad Zamarin
0:56:43 · Craig Shear, TUI Brothers · Over-engineering
Would new scaling projects be as over-engineered as the legacy projects?
Management expects to learn load profiles over time and may need less redundancy, so it is a fair observation. — Chad Zamarin