Rio Tinto (RIO) · Mining
Rio Tinto Q3 2026 earnings: summary, key numbers & outlook
Results filed 14 Oct 2026 · Quarter ended 30 Sep 2026
Press release ↗Investor relations ↗
Summaries and transcripts are machine-generated and can contain errors.
In brief
Simandou reached a ~10 Mtpa annualised run-rate as Rio Tinto ramps its new iron ore mine toward 60 Mtpa, while Oyu Tolgoi copper keeps growing and portfolio sales release capital.
Rio Tinto's copper and iron ore growth projects advanced. Oyu Tolgoi ran at a ~450 kt annualised rate, and Simandou hit a ~10 Mtpa run-rate and shipped 2.2 Mt to China. Kennecott's flash converting furnace was rebuilt ahead of plan. In aluminium, power agreements at Tomago and Bell Bay moved Pacific smelter repowering forward. Lithium production was hit by weather and a slower Sal de Vida ramp-up, though Fenix 1B is progressing well.
Management is steering toward copper, Simandou's ramp to 60 Mtpa in H2 2028, and lithium growth. It is funding this by selling assets: more than $2 billion of capital release so far, with Borates and Iron & Titanium under review. The tension is execution. Kennecott's seismic event, Sal de Vida delays, tariffs on US aluminium shipments, and Simandou's long supply chain to China all carry risk.
No call transcript for this quarter, so this summary also draws on: Rio Tinto ↗, The Motley Fool Australia ↗.
Key numbers
| Segment or metric | Value | Change |
|---|---|---|
| Oyu Tolgoi copper (metal in concentrates) | 114 kt | up 27% from Q3 2025 |
| Global iron ore sales (100% basis) | 90.8 Mt | up 3% from Q3 2025 |
| Pilbara iron ore sales (100% basis) | 85.7 Mt | up 2% from Q3 2025 |
| Total copper production (consolidated) | 205 kt | flat versus Q3 2025 |
| Lithium carbonate equivalent production | 13.0 kt | up 4% from Q3 2025 |
| Alumina production | 2.1 Mt | up 10% from Q3 2025 |
| Aluminium production | 0.8 Mt | down 2% from Q3 2025 |
| Simandou fines production (100%) | 2.5 Mt | up 273% from Q2 2026 |
Where each number comes from
- Oyu Tolgoi copper (metal in concentrates): “Oyu Tolgoi - Metal in concentrates 114 +27 % +17 % 312 +29 % Total copper production (consolidated basis1) 205 0 % -4 %”
- Global iron ore sales (100% basis): “Q3 global iron ore sales were 90.8 Mt, up 3% YoY, while Pilbara sales increased 2% YoY.”
- Pilbara iron ore sales (100% basis): “Pilbara iron ore sales7 (100% basis) Mt11 85.7 +2 % 0 % 243.3 +4 % 323 - 338 Unchanged”
- Total copper production (consolidated): “Copper production (consolidated basis) kt 205 0 % -4 % 646 +1 % 800 - 870 Unchanged”
- Lithium carbonate equivalent production: “Lithium carbonate equivalent (LCE) production10 kt 13.0 +4 % -11 % 40.3 +33 % 61 - 64 Unchanged (at lower end)”
- Alumina production: “Alumina production8 Mt 2.1 +10 % +3 % 6.1 +9 % 7.6 - 8.0 Unchanged”
- Aluminium production: “Aluminium production9 Mt 0.8 -2 % 0 % 2.52 0 % 3.25 - 3.45 Unchanged”
- Simandou fines production (100%): “Fines production (100%)1,2 2.5 NA +273 % 3.7 NA Fines shipped (100%) 2.2 NA +36 % 4.4 NA”
Copied from the press release ↗ and other documents in the SEC filing ↗. A figure is published only if its sentence is in those documents.
Outlook
| Metric | Period | Outlook |
|---|---|---|
| Copper production (consolidated basis) | 2026 | 800 - 870 kt |
| Global iron ore sales (100% basis) | 2026 | 343 - 366 Mt |
| Pilbara iron ore sales (100% basis) | 2026 | 323 - 338 Mt |
| Bauxite production | 2026 | 58 - 61 Mt |
| Alumina production | 2026 | 7.6 - 8.0 Mt |
| Aluminium production | 2026 | 3.25 - 3.45 Mt |
| Lithium carbonate equivalent production (expected at low end) | 2026 | 61 - 64 kt |
Key takeaways
Simandou is ramping toward 60 Mtpa by 2028
The mine reached a ~10 Mtpa run-rate in Q3 and shipped 2.2 Mt to China, with first ore through a primary crusher and the SimFer port expected in Q4 2026. Rio Tinto still targets full production rates in H2 2028.
Oyu Tolgoi underground ramp-up is driving copper growth
Oyu Tolgoi production rose 27% year on year as underground operations and recoveries improved, offsetting weakness at Kennecott and Escondida. Management still targets around 500 thousand tonnes a year from 2028 to 2036, with Panel 1 licence work in Mongolia ongoing.
Kennecott recovered but faces new geotechnical risks
The flash converting furnace rebuild finished at end-August ahead of plan after the June breach, and it is back at normal capacity. A 10 September seismic event at North Rim Skarn and ongoing open-pit access work leave mine plan impacts under assessment.
Asset sales are funding the growth portfolio
Rio Tinto has announced more than $2 billion of capital release year to date, including the Dampier desalination plant and Kitimat land sale to LNG Canada. It is on track to announce around $5 billion by end 2026 and is testing the market for Borates.
Lithium has strong demand but uneven execution
Battery storage shipments rose 94% year on year in eight months, but Rio Tinto expects full-year lithium output at the low end of guidance because Sal de Vida is ramping slower than planned. Fenix 1B is progressing well, and a Nemaska decision is expected in Q4 2026.
Questions
How is Simandou progressing?
Simandou reached an annualised production run-rate of ~10 Mtpa (100% basis) in Q3 and shipped 2.2 Mt to China. Rio Tinto remains on track for 60 Mtpa in H2 2028, with first ore through the SimFer port and a primary crusher expected in Q4 2026.
What is driving Rio Tinto's copper growth?
Oyu Tolgoi, where underground ramp-up and better recoveries lifted production 27% year on year in Q3. Kennecott and Escondida were weaker, from a furnace outage and lower feed grades, maintenance and weather respectively.
What is Rio Tinto doing in aluminium and decarbonisation?
Power agreements at Tomago and Bell Bay in Q3 advanced Pacific smelter repowering. The company also approved the Arctial project in Finland for feasibility, which would be the first AP60 smelter outside Quebec, and signed a low-carbon billet supply partnership with RevoCast.
What is the status of Rio Tinto's lithium business?
YTD production is up 33%, and Fenix 1B is ramping well. Sal de Vida is slower than expected, so full-year output is expected at the low end of guidance, and the Maricunga and Altoandinos joint ventures are expected to close in late 2026 or early 2027.
How is Rio Tinto managing its portfolio?
It has announced more than $2 billion of capital release year to date toward a $5–10 billion program. It is also reviewing Borates and Rio Tinto Iron & Titanium, and a final investment decision on the Kangwinan bauxite expansion is expected in Q4 2026.