0:14:14 · Michael Goldsmith, UBS · Rent outlook
How quickly can vacancy tighten and pricing power build if absorption stays at the normalized level while replacement-cost rents sit well above market rents?
Chris Caton declined to give a 2027 forecast but said demand and pipeline are promising, vacancy is on pace to reach 7% by year-end, and several markets already show 5% to 6% rent growth. — Chris Caton
0:17:10 · Michael Griffin, Evercore ISI · Development starts
How does a higher bar for development square with a modest increase in development starts guidance?
Dan Letter said the increase reflects a build-to-suit pipeline about 20 to 25% larger than last year, with a very large fourth quarter of build-to-suit starts expected. — Dan Letter
0:18:12 · Vikram Mahotra, Mizuho · Occupancy and rents
Why did the top of the occupancy guide tick down, and where is there evidence of mid-single-digit market rent growth?
Tim Arndt said it is a tightening of the range with further occupancy gains implied, and Chris Caton cited Dallas, Houston, Atlanta, Phoenix, Indianapolis, Northern California, Brazil and the Netherlands. — Tim Arndt, Chris Caton
0:20:23 · Tom Catherwood, BTIG · Acquisitions
Is Prologis now willing to buy assets whose mark-to-market upside is two to three years out?
Dan Letter said the approach is total return and discount to replacement cost, and the quarter's lower cap rates reflected one deal with a high lease mark-to-market. — Dan Letter, Tim Arndt
0:22:43 · Caitlin Burrows, Goldman Sachs · Transaction guidance
Why did acquisition guidance rise while contributions and dispositions fell?
Tim Arndt said acquisitions reflect activity to date, while disposition and contribution guidance reflects caution on volatile pricing and a couple of deals slipping into next year. — Tim Arndt
0:23:52 · Vince Tabone, Green Street · Cap rates
Does the 20 basis point rise in the stabilized cap rate on active development reflect a view on higher market cap rates?
Management said it reviews valuations of the pool regularly, already builds cap rate expansion into underwriting, and could not say the number reflects where values settle.
0:25:14 · John Kim, BMO Capital Markets · Data center leasing
What is holding up signing the roughly one gigawatt of data center letters of intent?
Dan Letter said there is no single constraint; negotiations with hyperscalers are long multi-billion-dollar decisions, and the letter-of-intent stage is being refilled as projects start. — Dan Letter
0:27:00 · Nicholas Uliko, Scotiabank · Southern California
How are Southern California submarkets performing across advanced manufacturing and traditional 3PL demand?
Chris Caton said the region is recovering, with the Inland Empire strong, Los Angeles varying by submarket, and aerospace-related Class A space in the South Bay moving quickly. — Chris Caton
0:29:33 · Nick Thillman, Baird · Lease economics
Is the rise in turnover costs due to mix, and have lease concessions peaked?
Tim Arndt said turnover costs reflect mix and occupancy building, and free rent declined sequentially but should bounce around before trending toward about 3% over the longer term. — Tim Arndt
0:31:07 · Michael Carroll, RBC Capital Markets · Demand drivers
Are higher rates holding back traditional industrial demand, offset by e-commerce and data center supply chain demand?
Chris Caton said conversations with customers remain constructive, data-center demand is outsized, and some rate-sensitive segments are slower. — Chris Caton
0:33:15 · Blaine Heck, Wells Fargo · SEGRO
Do rate moves affect SEGRO economics, and will initial 2027 guidance include SEGRO?
Tim Arndt said most of the financing is already set, closing is expected in the first half of 2027, and initial guidance will not include SEGRO. — Tim Arndt
0:35:16 · Dave Rogers, Raymond James · Data center moratoriums
Have data center moratoriums affected secured power or the pipeline, is the 17% share growing, and does it affect JV funding plans?
Management said the pipeline has not been affected, the 17% share is strengthening, and Prologis does not need a JV for data centers. — Chris Caton
0:38:23 · Todd Thomas, RBC Capital Markets · Return requirements
How have return requirements and data center underwriting changed with higher rates?
Tim Arndt said Prologis is applying extra caution and reserves in investment committee underwriting, and it builds buffers into data center returns while holding the margins it has quoted since 2023. — Tim Arndt