OpenNashEarnings

Dominion Energy (D) · Utilities

Dominion Energy Q2 2026 earnings: summary, key numbers & outlook

Results filed 31 Jul 2026 · Quarter ended 30 Jun 2026

Press release ↗Investor relations ↗

Summaries and transcripts are machine-generated and can contain errors.

In brief

Dominion Energy's data center contracted capacity reached about 53.8 GW while its NextEra Energy merger advanced and the Coastal Virginia Offshore Wind final turbine date slipped to year-end 2027.

Data center demand keeps building in Virginia: contracted capacity rose about 5.3 GW, or 11%, from December 2025, and more of it is moving to signed electric service agreements. Commercial sales growth is strong, customer counts are growing in Virginia and South Carolina, and South Carolina regulators unanimously approved an electric rate case settlement. Coastal Virginia Offshore Wind is about 81% complete, with all 176 monopiles and transition pieces installed.

Management is steering toward its proposed combination with NextEra Energy, expected to close in the second half of 2027 subject to approvals, while it executes a roughly $65B five-year capital plan. The main tension is that the offshore wind schedule slipped by two quarters and its capital budget rose to $11.65B, and the merger depends on shareholder and regulatory approvals across several agencies.

No call transcript for this quarter, so this summary also draws on: TIKR ↗, Baxtel ↗, Longbridge ↗, Quartr ↗.

Key numbers

Operating revenue · GAAP
$4.5B

up from $3,810 a year ago

Net income attributable to Dominion Energy · GAAP
$340 million

down from $760 million a year ago

Reported EPS, diluted · GAAP
$0.37

down from $0.88 a year ago

Operating earnings per share · non-GAAP
$0.79

up from $0.75 a year ago

Income from operations · GAAP
329.0M

down from 1,096 a year ago

Segment or metricValueChange
Dominion Energy Virginia operating earnings$670.0Mup from $549 a year ago
Dominion Energy South Carolina operating earnings105.0Mdown from 109 a year ago
Data center contracted capacity~53.8 GW~5.3GW/11% vs. December 2025
CVOW project completion~81% complete
Where each number comes from
  • Operating revenue: “Operating Revenue | $4,480 | $3,810 | $9,499 | $7,886 Operating Expenses Electric fuel and other energy-related purchases | 1,315 | 946”
  • Net income attributable to Dominion Energy: “for the three months ended June 30, 2026, of $340 million ($0.37 per share) compared with net income of $760 million ($0.88 per share) for the same period in 2025”
  • Reported EPS, diluted: “for the three months ended June 30, 2026, of $340 million ($0.37 per share) compared with net income of $760 million ($0.88 per share) for the same period in 2025”
  • Operating earnings per share: “Operating earnings (non-GAAP) for the three months ended June 30, 2026, were $712 million ($0.79 per share), compared to operating earnings of $649 million ($0.75 per share) for the same period in 2025”
  • Income from operations: “Income (loss) from operations | 329 | 1,096 | 1,721 | 2,319 Other income (expense) | 678 | 442 | 681 | 452”
  • Dominion Energy Virginia operating earnings: “By segment: Dominion Energy Virginia | $670 | $549 | $121 | $1,340 | $1,110 | $230 Dominion Energy South Carolina | 105 | 109 | (4)”
  • Dominion Energy South Carolina operating earnings: “By segment: Dominion Energy Virginia | $670 | $549 | $121 | $1,340 | $1,110 | $230 Dominion Energy South Carolina | 105 | 109 | (4)”
  • Data center contracted capacity: “~48.5 GW ~51.0 GW ~53.8 GW ~5.3GW/11% vs. December 2025 data center contracted capacity”
  • CVOW project completion: “Significant progress reduces project risk: ~81% complete (updated) Execution progress, operational achievements, and proven performance continue to reinforce confidence”

Copied from the press release ↗ and other documents in the SEC filing ↗. A figure is published only if its sentence is in those documents.

XBRL figures for this quarter arrive with the 10-Q or 10-K; the numbers above are from the press release.

Outlook

MetricPeriodOutlook
Operating earnings per sharefull-year 2026$3.45 to $3.69
Capital investment plan2026-2030~$65B
Dividend per share2026$2.67

Key takeaways

  1. Data center contracts grew to about 53.8 GW

    Contracted capacity is up about 5.3 GW, or 11%, since December 2025. About 12.0 GW now sits under electric service agreements, which define how customers take service and recover costs whether or not they take service.

  2. Offshore wind final turbine slips to year-end 2027

    Turbine installation projections added weather and vessel maintenance contingency, loadout time and extended jacking operations, an incremental two quarters. The project is about 81% complete, with 31 turbines installed and the third substation expected by year end 2026.

  3. NextEra Energy merger heads toward 2027 close

    Federal and state applications (FERC, NRC, HSR, NCUC, PSCSC, VSCC) are in process, and shareholder proxy materials were mailed around July 28, 2026. Close is expected in the second half of 2027, subject to approvals.

  4. Regulators delivered constructive outcomes

    South Carolina approved the electric rate case settlement unanimously, with new rates effective in July, the fourth consecutive base rate case settled there. Virginia also issued a final order approving 100% of the 2025 CVOW rider request.

  5. Millstone contract and Connecticut bid support New England

    Dominion Energy bid into Connecticut's zero carbon RFP, with decisions expected near term. Millstone's existing power purchase agreement is expected to save customers over $300M in 2026.

Charts

Revenue$5.0B+23.1% y/yQ1 2026
Q2 2024: $3.5BQ2 ’24$3.5BQ3 2024: $3.9BQ3 ’24$3.9BQ4 2024: $3.4BQ4 ’24$3.4BQ1 2025: $4.1BQ1 ’25$4.1BQ2 2025: $3.8BQ2 ’25$3.8BQ3 2025: $4.5BQ3 ’25$4.5BQ4 2025: $4.1BQ4 ’25$4.1BQ1 2026: $5.0BQ1 ’26$5.0B
Data
Q2 2024$3.5B
Q3 2024$3.9B
Q4 2024$3.4B
Q1 2025$4.1B
Q2 2025$3.8B
Q3 2025$4.5B
Q4 2025$4.1B
Q1 2026$5.0B
Diluted EPS (GAAP)$0.69−10.4% y/yQ1 2026
Q2 2024: $0.64Q2 ’24$0.64Q3 2024: $1.09Q3 ’24$1.09Q4 2024: $0.14Q4 ’24$0.14Q1 2025: $0.77Q1 ’25$0.77Q2 2025: $0.88Q2 ’25$0.88Q3 2025: $1.16Q3 ’25$1.16Q4 2025: $0.65Q4 ’25$0.65Q1 2026: $0.69Q1 ’26$0.69
Data
Q2 2024$0.64
Q3 2024$1.09
Q4 2024$0.14
Q1 2025$0.77
Q2 2025$0.88
Q3 2025$1.16
Q4 2025$0.65
Q1 2026$0.69

Fourth-quarter EPS appears once the press release is read; filings report it only for the full year.

Operating margin27.7%−2.3 pts y/yQ1 2026
Q2 2024: 23.1%Q2 ’2423.1%Q3 2024: 30.9%Q3 ’2430.9%Q4 2024: 11.5%Q4 ’2411.5%Q1 2025: 30.0%Q1 ’2530.0%Q2 2025: 28.8%Q2 ’2528.8%Q3 2025: 29.6%Q3 ’2529.6%Q4 2025: 18.5%Q4 ’2518.5%Q1 2026: 27.7%Q1 ’2627.7%
Data
Q2 202423.1%
Q3 202430.9%
Q4 202411.5%
Q1 202530.0%
Q2 202528.8%
Q3 202529.6%
Q4 202518.5%
Q1 202627.7%

Questions

How much data center demand is Dominion Energy contracting?

Data center contracted capacity reached about 53.8 GW in July 2026, up about 5.3 GW, or 11%, from December 2025. About 12.0 GW is under signed electric service agreements.

What happened to the offshore wind project schedule?

The final turbine target moved to year-end 2027, an added two quarters reflecting weather and vessel maintenance contingency, loadout time and extended jacking operations. The project is about 81% complete, with all 176 monopiles and transition pieces installed.

When is the NextEra Energy merger expected to close?

Subject to approvals, the merger is expected to close in the second half of 2027. Federal and state regulatory filings and shareholder meetings are still ahead.

How are customers and sales growing?

Weather normal commercial sales growth was 8.5% in the last twelve months, driven by data centers, and industrial load is under 10% of regulated sales. Electric customer growth is running 2.0% in Dominion Energy South Carolina and 0.9% in Dominion Energy Virginia.

What is the offshore wind project's cost position?

The capital budget is $11.65B including contingency, with about $9.8B invested and about $1.9B remaining. Unused contingency is $123M, and the levelized cost is $83/MWh versus a $125/MWh legislative prudency cap.

Documents

SEC filing