# Newmont (NEM) Q2 2026 earnings

Results filed 2026-07-23 for the quarter ended 2026-06-30. Source page: https://earnings.opennash.com/companies/nem/2026-q2/
Press release and documents: https://www.sec.gov/Archives/edgar/data/1164727/000116472726000034/0001164727-26-000034-index.htm
> Summaries and transcripts are machine-generated and can contain errors.

## In brief

Newmont restored Cadia to normal operations by mid-June after an April seismic event, while winning Red Chris Block Cave approvals and naming new executives to lead its next phase of delivery.

Newmont's quarter was shaped by operations. A seismic event at Cadia in April halted output there until mid-June, cutting copper production sharply, while Lihir, Boddington and Pueblo Viejo produced more. The company won British Columbia approvals for the Red Chris Block Cave, including a consent-based amended certificate with the Tahltan Nation. It also named new leaders for finance, operations, technology and project development.
Management is steering toward a heavier second half. Production is weighted 51% to H2, and development and sustaining capital are weighted toward the back half for Cadia panel caves, the Lihir Nearshore Barrier, tailings and Cerro Negro Expansion 1. The tension is delivery risk: output depends on mine sequencing, grades and project timing, and costs are exposed to higher oil prices and gold-linked royalties.

## Key numbers

| Metric | Value | Change | Basis |
| --- | --- | --- | --- |
| Sales | $6.1B |  | GAAP |
| Net income | $2.2 billion |  | GAAP |
| Diluted EPS | $2.06 |  | GAAP |
| Adjusted EPS | $2.10 |  | non-GAAP |
| Cash from operating activities | $2.9 billion | decreased 23 percent from the prior quarter | GAAP |
| Free cash flow | $2.2 billion | decreased 30 percent from the prior quarter | non-GAAP |
| Adjusted EBITDA | $3.8 billion |  | non-GAAP |

## Segments and operating metrics

| Name | Value | Change |
| --- | --- | --- |
| Attributable gold production | 1.3 million attributable gold ounces | decreased 1 percent from the prior quarter |
| Gold by-product AISC | $1,621 per ounce | increased 58 percent from the prior quarter |
| Average realized gold price | $4,414 per ounce | a decrease of $486 per ounce from the prior quarter |
| Copper production | 17 thousand tonnes | decreased 43 percent from the prior quarter |
| Nevada Gold Mines attributable gold production | 240 thousand ounces | increased 2 percent from the prior quarter |
| Pueblo Viejo attributable gold production | 74 thousand ounces | increased 37 percent from the prior quarter |

## Outlook

| Metric | Period | Outlook |
| --- | --- | --- |
| Attributable gold production | full year 2026 | 5.3 million attributable gold ounces |
| Gold by-product CAS per ounce | full year 2026 | $1,055 |
| Gold by-product AISC per ounce | full year 2026 | $1,680 |
| Sustaining capital | full year 2026 | $1.95 billion |
| Development capital | full year 2026 | $1.4 billion |
| Adjusted tax rate | full year 2026 | 33 percent |

## Key takeaways

1. **Cadia seismic event cut output, but mine recovered** Cadia production fell to 34 thousand ounces after the April seismic event, and copper dropped 43 percent from the prior quarter. Operations returned to normal levels as of mid-June, so the disruption looks contained to the quarter.
2. **Red Chris Block Cave cleared key BC approvals** Newmont received an amended Environmental Assessment Certificate, reached through a consent-based process with the Tahltan Nation, plus an amended Mines Act permit. This is a significant stage-gating milestone toward a final investment decision, which has not yet been made.
3. **Lihir Nearshore Barrier unlocks long-term ore access** Mobilization for the Nearshore Barrier at Lihir starts in the second half. It is expected to unlock access to over 5Moz beginning in 2028.
4. **Second-half ramp relies on several operations delivering** Production is expected to be about 51 percent weighted to H2, driven mainly by Boddington, Tanami, Lihir, Cerro Negro and Brucejack, partly offset by lower Yanacocha, Ahafo South and Merian. Third-quarter output is expected to be broadly in line with the second quarter.
5. **New executive team drawn from internal pipeline** Newmont appointed Brian Tabolt as CFO, Mark Rodgers as COO, David Thornton as Chief Technical Officer and David Fry as EVP Project Development, all from its internal talent pipeline. This positions leadership for the next phase of delivery.

## Questions

**What happened at Cadia this quarter?** A seismic event in April halted production, and Cadia produced 34 thousand attributable ounces. Operations returned to normal levels as of mid-June, though the downtime raised unit costs.
**What is the status of the Red Chris Block Cave project?** Newmont received an amended Environmental Assessment Certificate, achieved through a consent-based process with the Tahltan Nation, and an amended Mines Act permit. A final investment decision has not been made, and the feasibility study continues.
**How is Newmont's year expected to unfold operationally?** Newmont remains on track for its full-year production guidance, with about 51 percent of output expected in the second half. Third-quarter production should be broadly in line with the second quarter, with more weighting toward the fourth quarter.
**Which growth projects is Newmont advancing?** Development spend is focused on Cadia panel caves, Tanami Expansion 2, the Lihir Nearshore Barrier and Cerro Negro Expansion 1, plus the Red Chris feasibility study. Tanami's second expansion underground infrastructure is due to be completed and commissioned in Q3.
**Did Newmont change its leadership or guidance?** Newmont announced four executive appointments from its internal talent pipeline, including a new CFO and COO. It kept its 2026 guidance unchanged, including 5.3 million attributable gold ounces.