# Freeport-McMoRan (FCX) Q2 2026 earnings

Results filed 2026-07-23 for the quarter ended 2026-06-30. Source page: https://earnings.opennash.com/companies/fcx/2026-q2/
Press release and documents: https://www.sec.gov/Archives/edgar/data/831259/000083125926000033/0000831259-26-000033-index.htm
> Summaries and transcripts are machine-generated and can contain errors.

## In brief

Freeport's Grasberg Block Cave restart stayed on schedule while its U.S. leach program and Bagdad, Safford/Lone Star and El Abra expansion options advanced toward an America-centered copper growth strategy.

Freeport's Grasberg Block Cave ramp-up met its planned operating rates, with Production Blocks 2 and 3 restarted in March after the September 2025 mud rush incident. In the Americas, leach technology added 47 million pounds of copper in the quarter, Morenci ran well above its five-year average, and Freeport bought more of Cerro Verde, lifting its stake to 55.66%.
Management is steering toward growth in the Americas through leach innovation, a possible Bagdad doubling, Safford/Lone Star studies and a large El Abra mill, while restoring Grasberg and seeking a license extension beyond 2041. The tension is execution: Bagdad capital costs are about 30% above the 2023 estimate, Grasberg still needs years to reach full capacity, and Indonesian approvals have no fixed timeline.

## Key numbers

| Metric | Value | Change | Basis |
| --- | --- | --- | --- |
| Revenues | $7.0B | down from $7,582 a year ago | GAAP |
| Net income attributable to common stock | $984 million | up from $772 million a year ago | GAAP |
| Diluted EPS | $0.68 | up from $0.53 a year ago | GAAP |
| Adjusted EPS | $0.74 | up from $0.54 a year ago | non-GAAP |
| Operating income | $2.0B | down from $2,432 a year ago | GAAP |
| Operating cash flows | $2.0B | down from $2,195 a year ago | GAAP |

## Segments and operating metrics

| Name | Value | Change |
| --- | --- | --- |
| Consolidated copper sales (million pounds) | 710 | down from 1,016 a year ago |
| U.S. copper sales (million pounds) | 312 | up from 308 a year ago |
| South America copper sales (million pounds) | 245 | down from 265 a year ago |
| Indonesia copper sales (million pounds) | 153 | down from 443 a year ago |
| Consolidated gold sales (thousand ounces) | 123 | down from 522 a year ago |
| Consolidated molybdenum sales (million pounds) | 25 | up from 22 a year ago |
| Average realized copper price per pound | $6.17 | up from $4.54 a year ago |
| Unit net cash costs per pound of copper | $1.97 | up from $1.13 a year ago |

## Outlook

| Metric | Period | Outlook |
| --- | --- | --- |
| Copper sales volume | third quarter of 2026 | 750 million pounds |
| Copper sales volume | year 2026 | 3.1 billion pounds |
| Unit net cash costs per pound of copper | year 2026 | $1.90 per pound |
| Unit net cash costs per pound of copper | third quarter of 2026 | $2.00 per pound |
| Capital expenditures | year 2026 | $4.3 billion |
| Operating cash flows | year 2026 | $8.3 billion |
| Consolidated effective tax rate | year 2026 | 30% |

## Key takeaways

1. **Grasberg ramp-up is on schedule after mud rush** Production Blocks 2 and 3 achieved planned operating rates in the second quarter, and PTFI expects about 65% of capacity in the second half of 2026, 80% by mid-2027 and near full capacity by the end of 2027. Production Block 1S restart is targeted for mid-2027.
2. **Leach technology is becoming a growth engine** Leach initiatives added 47 million pounds in the quarter, with a target run rate of 300 million pounds by end of 2026 and about 800 million by 2030. Freeport is testing internally developed additives at Morenci and heat on stockpiles.
3. **Bagdad doubling nears a decision despite higher costs** Studies point to 200 to 250 million additional pounds of copper annually, with a potential investment decision in the second half of 2026. Capital cost is estimated about 30% above the prior $3.5 billion, though economics are still supported at roughly $4.00 per pound copper.
4. **El Abra mill could add over 700 million pounds** El Abra submitted its environmental impact study in March 2026, with roughly two to three years of permitting and four years of construction, implying a start-up in the 2033 timeframe. It is a major South American growth option, contingent on permits and market conditions.
5. **Indonesia license extension is applied for, not secured** After a February 2026 MOU, PTFI applied in June for extension of its mining license beyond 2041, under which Freeport would hold about 37% from 2042. Approval timing is uncertain and remains a stated risk.

## Questions

**Is the Grasberg Block Cave restart on track?** Yes. PTFI met its planned operating rates in the second quarter, and expects roughly 65% of capacity in the second half of 2026, 80% by mid-2027 and near full capacity by the end of 2027.
**What are Freeport's main copper growth projects?** Leach technology (targeting about 300 million pounds run rate by end of 2026), a Bagdad concentrator doubling, Safford/Lone Star expansion studies and a major El Abra mill. Kucing Liar in Indonesia is planned to ramp up from around 2030.
**What is happening with the Bagdad expansion?** Freeport is finalizing capital estimates, now about 30% above the prior $3.5 billion, and may make an investment decision in the second half of 2026. It would add 200 to 250 million pounds of copper a year and take three to four years to build.
**Where does Freeport stand on extending its Indonesian operating rights?** It signed an MOU with the Indonesian government in February 2026 and submitted its license extension application in June. Management has said there is no prescribed timeline for approval.
**Why did Freeport buy more of Cerro Verde?** It bought 2.0 million shares in the open market for $107 million, raising its stake from 55.08% to 55.66%. The sources do not state a specific motive.