# Exelon (EXC) Q2 2026 earnings

Results filed 2026-07-30 for the quarter ended 2026-06-30. Source page: https://earnings.opennash.com/companies/exc/2026-q2/
Press release and documents: https://www.sec.gov/Archives/edgar/data/1109357/000110935726000077/0001109357-26-000077-index.htm
> Summaries and transcripts are machine-generated and can contain errors.

## In brief

Exelon pairs a data-center and transmission pipeline with utility-owned battery storage and virtual power plants as it pursues affordable, reliable power amid surging demand.

Exelon's six regulated utilities filed new storage proposals, including a transmission-connected battery system of up to 500 MW at Atlantic City Electric built with Invenergy. ComEd won approval to launch its first virtual power plant program, expected by March 2027. BGE filed an electric distribution rate case, and all utilities project top quartile reliability. Data-center demand is the main growth driver, with about 11 GW of high-probability load.
Management is steering toward more transmission, storage and virtual power plants, with $12-17B of transmission opportunity beyond its $41.7B capital plan. The tension is affordability: new rate cases, large-load protections and rising customer costs must coexist with heavy investment. Some storage and transmission projects are still awaiting regulatory approval, and the plan relies on about $3.4B of new equity through 2029.

## Key numbers

| Metric | Value | Change | Basis |
| --- | --- | --- | --- |
| GAAP EPS | $0.39 | relatively consistent with the prior period at $0.39 per share | GAAP |
| Adjusted operating EPS | $0.43 | up from $0.39 in the second quarter of 2025 | non-GAAP |
| Operating revenues | $6.0B | up from $5,427 a year ago | GAAP |
| Operating income | $979.0M | up from $927 a year ago | GAAP |
| Net income | $396.0M | up from $391 a year ago | GAAP |
| Operating cash flow (six months) | 3.7B | up from 2,711 a year ago | GAAP |

## Segments and operating metrics

| Name | Value | Change |
| --- | --- | --- |
| ComEd adjusted operating earnings | $249 | up from $228 million |
| PECO adjusted operating earnings | $130 | down from $136 million |
| BGE adjusted operating earnings | $70 | up from $55 million |
| PHI adjusted operating earnings | $126 | down from $144 million |

## Outlook

| Metric | Period | Outlook |
| --- | --- | --- |
| Adjusted operating EPS | full year 2026 | $2.81-$2.91 per share |

## Key takeaways

1. **ACE proposes up to 500 MW battery storage** Atlantic City Electric, partnered with Invenergy, filed a utility-owned storage project for construction by late 2030. It was submitted to PJM's queue and to the New Jersey Board of Public Utilities, with no customer bill impact projected through at least 2035.
2. **Virtual power plants gain regulatory approval** The ICC approved ComEd's Scheduled Dispatch VPP, expected to launch by March 2027, and 173.5 MW was approved for BGE and Pepco Holdings pilots. This extends Exelon's role from delivering power to orchestrating customer-owned flexibility.
3. **Data-center pipeline anchored by Transmission Security Agreements** About 11 GW of high-probability data-center load is in advanced design or backed by FERC-approved agreements, with about 40% of ComEd's near-term load under such agreements backed by about $1B in collateral. FERC endorsed the framework, which filters out speculative projects and protects existing customers.
4. **Transmission opportunity extends beyond the plan** Exelon sees $12-17B of transmission opportunity beyond its plan, including $1.2B of investment approved in PJM's RTEP Window #1 and a $1B+ MISO Tranche 2.1 project. Data centers, generator deactivations and congestion are driving the need.
5. **BGE files electric rate case amid affordability pressure** BGE requested a $156 million increase in July, with a decision expected in the first quarter of 2027. Pepco Maryland and DPL Delaware cases remain on track, so regulators' response will shape how Exelon balances investment against bills.

## Questions

**What storage project did Exelon announce this quarter?** Atlantic City Electric, partnered with Invenergy, proposed up to 500 MW of utility-owned battery storage in New Jersey, targeted for construction by late 2030. It was submitted to PJM's interconnection queue and filed with the New Jersey Board of Public Utilities.
**How is Exelon approaching data-center demand?** It uses Transmission Security Agreements that require signed commitments and collateral, which FERC has endorsed as a model. Exelon cites about 11 GW of high-probability data-center load across ComEd and the Mid-Atlantic.
**What are virtual power plants doing at Exelon?** ComEd's Scheduled Dispatch VPP was approved by the ICC and is expected to launch by March 2027. BGE and Pepco Holdings have 173.5 MW approved for pilots.
**Where is Exelon looking for growth beyond its current capital plan?** Management points to $12-17B of transmission opportunity beyond the plan, including competitive projects in and outside PJM and a $1B+ MISO Tranche 2.1 project.
**What regulatory decisions are coming up?** BGE's electric rate case decision is expected in the first quarter of 2027, and Pepco Maryland's order is expected in August 2026. ComEd's grid plan order is expected by December 15, 2026.